Lowari Tunnel Southern Portal Access Road
Project Name Lowari Tunnel Southern Portal Access Road
Length 9 Km
Cost (In Million) Amir Muqam
Contractor EMS
Consultant TECHNO
Date of Commencement 21 April 2004
Approved Date of Completion 30 September 2007
Expected Date of Completion 31 October 2008
Physical Progress 93/100 % Completed