Lowari Main Tunnel
Project Name Lowari Main Tunnel
Length  8.75 km
Cost (In Million) 5545.7
Contractor Sambu(JV)
Consultant Geo-Consult/Typsa JV
Date of Commencement 5 September 2005
Approved Date of Completion 4 September 2010
Expected Date of Completion 30 September 2010
Physical Progress 87.1% completed